Footings poured for walls 11-16-2004
|
|
|
|
Excavation for foundation 11-15-2004
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
 |
|
|
|
|
The Rock! In the middle of the new driveway!
|
|
|
|
Cement walls poured 11-19-2004
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
 |
|
|
|
|
|
Basement - Garage Framing Started 01-25-2005
|
|
|
Foundation Complete and Back-Filled
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
 |
|
|
|
|
First wall up for Family Room 01-27-2005
|
|
|
Update Jan. 30, 2005 Walls up for new Family Room.
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
 |
|
|
|
|
Update Feb. 2, 2005 Roof Removal
|
|
|
|
|
|
|
Update Feb. 11, 2005
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
|
 |
|
|
|
|
|
Dormers.... Roofing Started... Update Feb. 24, 2005
|
|
|
|
Update Feb. 19, 2005 Start of 3rd Floor Changes
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
 |
|
|
|
Roof Complete Dormers finished... Update Feb. 26, 2005
|
|
|
|
|
|
|
Siding Complete March 4, 2005
|
|
|
|
|
|
|
|
|
|
 |
|
|
|
Almost Complete.... Insulation, Plaster, ready for paint! May 13, 2005
|
|
|
|
|
 |
|
Still Not Done...
Driveway, painted, waiting for finish from contractor and carpet! July 10, 2005
|
|
|
|
|
|
|
|
|
|
|
|
|
 |
|
September 10, 2005
Wood floor, wood stairs installed by us, painting almost done, all carpet complete. Yard is getting put in this week and driveway is getting paved.
|
|
|
|
|
 |
|
|
|
|
|
September 26, 2005
Yard landscaped and seeded, driveway paved, and porch finished!
|
|
|
|
|
|
|
|
|
|
|